Track laying is well advanced with 75% assembled. The Major Civil engineering feature is the creation of a completely new Pond area with the railway running around the edge and a new steel span bridge. Works are well advanced and track laying on this section will start in July. meanwhile our team have been bringing the other sections up final top and horizontal alignment.